Abandonment and Relocation of the San Diego Country Club Pipeline RFP
Posted
Oct 9, 2026
Oct 30, 2026
Work includes 1 LS diversion of recyclable waste materials; 1 LS sheeting, shoring, and bracing, or equivalent method; 1 LS clean and inspect existing 30" cml&c steel pipe before sliplining; 3,578 LF provide and install 24" HDPE pipe via sliplining within existing 30" cml&c pipe, disinfect and test new pipeline ; 5 EA excavate slipline insertion/receiving pit, demolish existing 30" cml&c steel pipe as required, backfill and restore surface in kind; 1 LS sta 10+00: connect to existing 30" cml&c steel watermain and install approximately 10 LF of 24" cml&c steel pipe, with 24" butterfly valve, 6" blowoff assembly, and 4" air-vac assembly, connect 24" cml&c steel pipe to 24" HDPE pipe. See outside link.